Crane closings to DeSoto Street entrance - April/May/June

image

A large crane will be placed in front of the DeSoto Street/Main Parran Lobby entrance during specific dates in late April, May, and June. closing that entrance for the day. The Fifth Avenue entrance near the G23 Auditorium as well as the garage and loading dock entrances will be available. Upcoming crane hoisting dates include:

  • 4-26-17    Hoist Air Handler 8-4 crane setup at main entrance.     
  • 5-3-17      Hoist pipe and ductwork setup at main entrance. Additionally the same day with the same crane, McKamish will setup on Bouquet Street remove rooftop equipment (Hoist plans forthcoming) Mckamish to coordinate with PJD, Pitt parking, and Benedum Hall Alleyway access if so affected.
  • 5-31-17    Hoist Air handler 8-3 setup at main entrance (Hoisting plan forthcoming)
  • 6-7-17      Last duct work and shaft top setup at main entrance (Hoisting plan forthcoming)
  • 6-20-17    Last crane at front entrance to remove scissor lifts / materials / remove landing platform (Hoist plan will be provided)


4/19/2017